High risk
  • Possession date passed. The proposed possession date (Jan 2019) has passed with construction at 66.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2019 per the RERA filing.

Area guide

What it's like to buy in Bela (CT)

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
BALAJI BUILDERS AND DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P50600009251
Status
Ongoing
Stage
Certificate Signed
Possession
January 2019
Construction
66.4% complete
Units sold
0 of 0