YASHRAJ GARDEN PHASE 1
MahaRERA P51500015997High risk
GUT No 172 173 AT SAWANGI, AURANGABAD, 431001
Post your property hereOwn or renting out a unit in YASHRAJ GARDEN PHASE 1? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in AURANGABAD come to you.
Sept 2020
Possession
41.8%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 41.8%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Sept 2020 per the RERA filing.
Promoter
Builder profile
YASHRAJ INFRASTRUCTURE
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51500015997
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2020
- Construction
- 41.8% complete
- Units sold
- 0 of 0
Similar projects in AURANGABAD
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
SHRI JYOTIDARSHAN
AURANGABAD95.5% builtPoss. August 2024
Sakshi Varad Vinayak Phase II
AURANGABAD90.9% builtPoss. October 2018
TAPADIA SUKHVASTU
AURANGABAD90.9% builtPoss. December 2023
PAHADE ORCHID
AURANGABAD90.9% builtPoss. September 2024
SAI ASPIRE
AURANGABAD90.9% builtPoss. January 2021
31-NATIONAL
AURANGABAD81.8% builtPoss. January 2026
SAI SAHYOG RESIDENCY
AURANGABAD81.8% builtPoss. November 2021
MALKHARE APARTMENT
AURANGABAD78.6% builtPoss. March 2027