Under construction
AJAY HEIGHTS
MahaRERA P51500019612High risk
GAT NO - 57 PART, SATARA, 431005
Post your property hereOwn or renting out a unit in AJAY HEIGHTS? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in SATARA come to you.
Mar 2023
Possession
72.7%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Mar 2023) has passed with construction at 72.7%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2023 per the RERA filing.
Area guide
What it's like to buy in SATARA
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
SHRINIWAS INFRA
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51500019612
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2023
- Construction
- 72.7% complete
- Units sold
- 0 of 0
Similar projects in SATARA
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
GREEN SPACE RESIDENCY PROJECT 2
SATARAPoss. March 2024
MALHAR APARTMENT
SATARAPoss. December 2028
BALAJI RESIDENCY
SATARA100% builtPoss. December 2021
VINAYAK SRUSHTI
SATARA90.9% builtPoss. December 2023
AVANEESH RESIDENCY
SATARA90.9% builtPoss. December 2018
PUSHPAJAL APT.
SATARA90.9% builtPoss. September 2020
POOJA RESIDENCY
SATARA90.9% builtPoss. July 2019
SIDDHIVINAYK TOWER
SATARA90.9% builtPoss. December 2018
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.