PropPin
High risk
  • Possession date passed. The proposed possession date (Jul 2024) has passed with construction at 25%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2024 per the RERA filing.

Promoter

Builder profile

Builder
SSD BUILDERS AND DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51500030314
Status
New
Stage
Certificate Signed
Possession
July 2024
Construction
25% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.