High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2025, now proposed Dec 2029 per the RERA filing.

Promoter

Builder profile

Builder
ARHAM BUILDERS AND DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
MANOJ KALA AND ASSOCIATES KALA

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51500031188
Status
New
Stage
Certificate Signed
Possession
December 2029originally December 2025
Construction
96.4% complete
Units sold
22 of 125

Similar projects in GARKHEDA PARISAR