SUYOJIT ONE WORLD PHASE-II, COMMERCIAL AND HOSPITAL

MahaRERA P51600002585High risk

by SUN INFRASTRUCTURES PVT. LTD

OUT OF SURVEY NO. 113/A/3-2, 113/A/1A/6, 113/B CTS NO. 4444P,4450,4453,4448,4449,4451A,4452, NEAR BIRLA HOSPITAL, NASHIK ROAD, 422101

Official record
Dec 2022
Possession
72.7%
Built
1
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Mar 2019, now proposed Dec 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 72.7%.

Promoter

Builder profile

Builder
SUN INFRASTRUCTURES PVT. LTD

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600002585
Status
Ongoing
Stage
Certificate Signed
Possession
December 2022originally March 2019
Construction
72.7% complete
Units sold
0 of 0