PropPin
All RERA projects
🏗️
Under construction

PADMAVATI NAGARI BLDG NO 1 A and B wing

MahaRERA P51600003238High risk

by S D BHALERAO CONSTRUCTIONS PVT LTD

GUT NO 162 PLOT NO 15 TO 18 AND 35 TO 38, Venkatesh Nagar, 422403

Official record
Oct 2020
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2018, now proposed Oct 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 90.9%.

Promoter

Builder profile

Builder
S D BHALERAO CONSTRUCTIONS PVT LTD

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51600003238
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020originally December 2018
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Venkatesh Nagar

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.