  • Possession date passed. The proposed possession date (Mar 2020) has passed with construction at 72.7%.

Area guide

What it's like to buy in DGP NAGAR

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Pacific Builders

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600007154
Status
Ongoing
Stage
Certificate Signed
Possession
March 2020
Construction
72.7% complete