Under construction

EKA PHASE III - F BUILDING

MahaRERA P51600008507High risk

by Amit Builders

S. No. 1/1, 1/2, 1/3, 1/4 AND 1/5 Pathardi, Nashik., Pathardi, 422010

Official record
Jun 2023
Possession
90.9%
Built
3
Complaints
0
Units
High risk
  • Litigation pending (4). MahaRERA's litigation disclosure lists 4 pending cases against this project.
  • Possession delayed ~3 yrs. Originally promised Dec 2019, now proposed Jun 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 90.9%.

Promoter

Builder profile

Builder
Amit Builders

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600008507
Status
Ongoing
Stage
Certificate Signed
Possession
June 2023originally December 2019
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Pathardi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.