High risk
  • Possession delayed ~1 yr. Originally promised Aug 2019, now proposed Oct 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 59.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2020 per the RERA filing.

Promoter

Builder profile

Builder
VASTULAXMI BUILDERS AND CONTRACTORS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600008523
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020originally August 2019
Construction
59.1% complete
Units sold
0 of 0