PropPin
High risk
  • Possession date passed. The proposed possession date (Jun 2020) has passed with construction at 50%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2020 per the RERA filing.

Promoter

Builder profile

Builder
ARUN PUNDLIK NIKAM

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600010591
Status
Ongoing
Stage
Certificate Signed
Possession
June 2020
Construction
50% complete
Units sold
0 of 0

Similar projects in Nashik

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.