High risk
  • Possession delayed ~8 yrs. Originally promised Dec 2019, now proposed Mar 2028 per the RERA filing.
Ghatkopar / VikhroliUpper-mid

Metro-1 anchor with Godrej's Vikhroli land bank next door.

Growth drivers:
Metro 1 interchange, Eastern Express Highway, corporate campuses.
Who buys here:
Families wanting east-side connectivity to BKC/Fort.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
NANDAN BUILDCON PVT LTD

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
DISIGN SQUARE ASSOCIATES

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51600012372
Status
Ongoing
Stage
Certificate Signed
Possession
March 2028originally December 2019
Construction
57.1% complete
Units sold
7 of 104

Similar projects in ADGAON

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.