Under construction
Ajinkya Heights
MahaRERA P51600015402High risk
52 plus53plus54/93/2/A, Gangapur, 422013
Post your property hereOwn or renting out a unit in Ajinkya Heights? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Gangapur come to you.
Feb 2022
Possession
43.2%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Feb 2022) has passed with construction at 43.2%.
Area guide
What it's like to buy in Gangapur
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Anand Constructions
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51600015402
- Status
- New
- Stage
- Certificate Signed
- Possession
- February 2022
- Construction
- 43.2% complete
- Units sold
- 0 of 0
Similar projects in Gangapur
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
GANRAJ SANKUL
GangapurPoss. March 2029
CHHATRAPATI NAGAR
GangapurPoss. March 2030
Sai Nisarg Apartment
GangapurPoss. November 2028
Aarambh Apartment
Gangapur66.4% builtPoss. December 2026
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.