All RERA projects
🏗️
Under construction
Viraj Park
MahaRERA P51600019771High risk
Survey no 54/2 Plot no 6 plus 7 plus 8, Gangapur Shiwar, 422007
Post your property hereOwn or renting out a unit in Viraj Park? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Gangapur Shiwar come to you.
Feb 2022
Possession
90.9%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Feb 2022) has passed with construction at 90.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Feb 2022 per the RERA filing.
Promoter
Builder profile
Vira Enterprises
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51600019771
- Status
- New
- Stage
- Certificate Signed
- Possession
- February 2022
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Gangapur Shiwar
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Ashok Pride
Gangapur Shiwar100% builtPoss. November 2024
OMKARA PARK WING A
Gangapur Shiwar100% builtPoss. June 2023
Samruddhi Heights Appartment
Gangapur Shiwar90.9% builtPoss. March 2028
KRUSHNA HEIGHT
Gangapur Shiwar90.9% builtPoss. March 2026
Vaishnavi Heights
Gangapur Shiwar90.9% builtPoss. December 2024
Gokul 5
Gangapur Shiwar90.9% builtPoss. December 2022
OM GURUDEV RESIDENCY
Gangapur Shiwar90.9% builtPoss. July 2022
SWANANDI BLOSSOM
Gangapur Shiwar90.9% builtPoss. December 2021
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.