CONSTRUCTION OF 154 TS EWS I AND 24 TS EWS II TOTAL 178 TS ON S NO 36/B/1 AT KAMATHWADE NASHIK
MahaRERA P51600019848High risk
by Nashik Housing and Area Development Board
36/B/1, KAMATHWADE, 422008
Post your property hereOwn or renting out a unit in CONSTRUCTION OF 154 TS EWS I AND 24 TS EWS II TOTAL 178 TS ON S NO 36/B/1 AT KAMATHWADE NASHIK? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in KAMATHWADE come to you.
Dec 2023
Possession
90.9%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 90.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.
Promoter
Builder profile
Nashik Housing and Area Development Board
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51600019848
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2023
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in KAMATHWADE
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
SAI ASHIRWAD
KAMATHWADE100% builtPoss. July 2023
SHIV RANJANI
KAMATHWADE65.9% builtPoss. May 2024
TATHAASTU
KAMATHWADE52.7% builtPoss. December 2024
SAPTASHRUNGI CASTLE
KAMATHWADE52% builtPoss. June 2025
YASH HEIGHTS
KAMATHWADE9.1% builtPoss. December 2024
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.