NILKANTH APARTMENT

MahaRERA P51600020697Caution

by NILKANTH INFRA

SURVEY NO 10/3/B PLOT NO 1 PLUS 2, MAKHMALABAD, 422003

Official record
May 2025
Possession
90.9%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (May 2025) has passed with construction at 90.9%.

Promoter

Builder profile

Builder
NILKANTH INFRA

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600020697
Status
New
Stage
Certificate Signed
Possession
May 2025
Construction
90.9% complete
Units sold
0 of 0