PropPin
High risk
  • Possession date passed. The proposed possession date (Feb 2025) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Feb 2025 per the RERA filing.

Promoter

Builder profile

Builder
Sairaj associates

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600024922
Status
New
Stage
Certificate Signed
Possession
February 2025
Construction
90.9% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.