High risk
  • Possession date passed. The proposed possession date (Feb 2023) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Feb 2023 per the RERA filing.

Promoter

Builder profile

Builder
MORYA CONSTRUCTIONS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600025188
Status
New
Stage
Certificate Signed
Possession
February 2023
Construction
81.8% complete
Units sold
0 of 0