PropPin
Caution
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 81.8%.

Area guide

What it's like to buy in MAKHAMALABAD SHIVAR PETH ROAD, NEAR APMC MARKET

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
SHREE INFRA PROJECT

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600026362
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
81.8% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.