PropPin
High risk
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 58.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.

Promoter

Builder profile

Builder
SHRI VRINDAVAN BUILDERS & DEVELOPERS LLP

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600027562
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
58.7% complete
Units sold
0 of 0

Similar projects in DWARKA

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.