High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 59.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2025 per the RERA filing.

Promoter

Builder profile

Builder
KAMDHENU ENTERPRISES

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600031450
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
59.5% complete
Units sold
0 of 0