PropPin
High risk
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 55.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.

Promoter

Builder profile

Builder
H K PROPERTIES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51600034290
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
55.5% complete
Units sold
0 of 0

Similar projects in Anandwali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.