Under construction
THREE LEAVES PHASE ONE
MahaRERA P51600047728High risk
by DEEPAK INFRA AND HOMES PRIVATE LIMITED
S NO 789/3, GOVIND NAGAR, 422009
Post your property hereOwn or renting out a unit in THREE LEAVES PHASE ONE? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in GOVIND NAGAR come to you.
Dec 2030
Possession
17.7%
Built
0
Complaints
256
Units
High risk
- Mortgaged to a lender (₹74 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹74 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
Area guide
What it's like to buy in GOVIND NAGAR
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
DEEPAK INFRA AND HOMES PRIVATE LIMITED
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51600047728
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2030
- Construction
- 17.7% complete
- Units sold
- 110 of 256
Similar projects in GOVIND NAGAR
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
BUSINESS WORLD
GOVIND NAGAR95.5% builtPoss. December 2023
AMRUT PUSHP A
GOVIND NAGAR90.9% builtPoss. December 2026
THE RENAISSANCE
GOVIND NAGAR90.9% builtPoss. December 2018
Orchard Meadow
GOVIND NAGAR90.9% builtPoss. August 2019
LOTUS PARK
GOVIND NAGAR90.9% builtPoss. July 2024
HARI OM HARMONY APT
GOVIND NAGAR90.9% builtPoss. December 2024
BLUE LOTUS
GOVIND NAGAR84.5% builtPoss. March 2024
ADVAIT APARTMENT
GOVIND NAGAR81.8% builtPoss. December 2025
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.