Under construction
SUKRUTI NILAYA
MahaRERA P51600048811High risk
Plot No 4 and 5 S N65/3/3/1/1, GANGAPUR ROAD, 422013
Post your property hereOwn or renting out a unit in SUKRUTI NILAYA? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in GANGAPUR ROAD come to you.
Dec 2024
Possession
11.8%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 11.8%.
Area guide
What it's like to buy in GANGAPUR ROAD
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
SUKRUTI CONSTRUCTIONS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51600048811
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2024
- Construction
- 11.8% complete
- Units sold
- 0 of 0
Similar projects in GANGAPUR ROAD
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
HARI VASANT
GANGAPUR ROADPoss. September 202631 complaints
KRISHNA KRUPA APARTMENT
GANGAPUR ROAD90.9% builtPoss. December 20221 complaint
SHREE TIRUMALA LUXURIA APARTMENT
GANGAPUR ROAD90.9% builtPoss. April 2023
SHREEMALHAR APARTMENT
GANGAPUR ROAD90.9% builtPoss. December 2025
SAISRENITY-B
GANGAPUR ROAD90.9% builtPoss. December 2022
GOKULDHAM APARTMENT
GANGAPUR ROAD81.8% builtPoss. May 2022
PARTH RESIDENCY
GANGAPUR ROAD81.8% builtPoss. January 2024
TORNA
GANGAPUR ROAD81.4% builtPoss. October 2024
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.