Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Promoter

Builder profile

Builder
SARATHI CONSTRUCTION COMPANY

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51600049267
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
60.9% complete
Units sold
0 of 0