Under construction

Feriha Heights

MahaRERA P51600055909High risk

by Aroma Developers

Plot No- 20+21, Survey No- 113/3/11 to 16/21 to 23, Wadala, Shiwar, 422007

Official record
Mar 2027
Possession
49.1%
Built
0
Complaints
28
Units
High risk
  • Behind schedule. Possession is due Mar 2027 but construction is only at 49.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Promoter

Builder profile

Builder
Aroma Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600055909
Status
New
Stage
Certificate Signed
Possession
March 2027originally March 2026
Construction
49.1% complete
Units sold
13 of 28