PropPin
High risk
  • Mortgaged to a lender (₹45 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹45 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Mar 2027 per the RERA filing.
  • 50 RERA complaints. 50 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Mar 2027 per the RERA filing.
Dahisar / Mira RoadValue

The city's northern value frontier, densifying fast.

Growth drivers:
Metro 9 extension, spillover from Borivali pricing.
Who buys here:
First-time buyers stretching for a 1–2 BHK.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Ravi Developments

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700006232
Status
Ongoing
Stage
Certificate Signed
Possession
March 2027originally December 2023
Construction
70.1% complete
Units sold
375 of 489

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.