High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2019, now proposed Dec 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 90.9%.

Promoter

Builder profile

Builder
DEV VENTURES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700006775
Status
Ongoing
Stage
Certificate Signed
Possession
December 2020originally June 2019
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Badlapur (M Cl)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.