PropPin
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Promoter

Builder profile

Builder
Aniline Construction Company Private Limited

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Saakaar

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700007024
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally March 2026
Construction
65.1% complete
Units sold
420 of 420

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.