Under construction
MAMTA 1351
MahaRERA P51700007648High risk
by PATIL GROUP BUILDERS AND DEVELOPERS
CTS NO 773, 774, 775, TITWALA, 421605
Post your property hereOwn or renting out a unit in MAMTA 1351? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in TITWALA come to you.
Dec 2026
Possession
83.6%
Built
0
Complaints
84
Units
High risk
- Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Dec 2026 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Promoter
Builder profile
PATIL GROUP BUILDERS AND DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Architect
Design profile
MR RAJEEV TAISHETE
Browse other projects associated with this architect to compare design and delivery patterns.
No other projects are linked to this architect yet.
Official RERA facts
- Registration
- P51700007648
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2022
- Construction
- 83.6% complete
- Units sold
- 53 of 84
Similar projects in TITWALA
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
UMA GALAXY
TITWALA94.1% builtPoss. December 2022
RUSTTAGI AARAMBHA PHASE-III
TITWALA90.9% builtPoss. February 2027
SADGURU NAKSHTRA PHASE I
TITWALA90.9% builtPoss. December 2023
SIDHESHWAR COMPLEX BUILDING 1 A WING
TITWALA90.9% builtPoss. December 2017
SADGURU NAKSHTRA PHASE II
TITWALA90.9% builtPoss. October 2023
ASHOKA HEIGHTS
TITWALA90.9% builtPoss. December 2022
DIYA WOODS
TITWALA89.1% builtPoss. January 2025
RAMDARSHAN RESIDENCY
TITWALA83.2% builtPoss. February 2027
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.