High risk
  • Litigation pending (5). MahaRERA's litigation disclosure lists 5 pending cases against this project.
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) β€” a stronger signal than the complaint being merely filed.
  • Possession delayed ~2 yrs. Originally promised Dec 2019, now proposed Dec 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 90.9%.

Area guide

What it's like to buy in Ambarnath East

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Ambernath / BadlapurValue

The value frontier beyond Kalyan β€” low-rise affordability, improving rail links.

Growth drivers:
Extended suburban rail, industrial-belt employment, lowest entry prices in MMR.
Who buys here:
First-home buyers stretching every rupee.

PropPin area guide β€” editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Lok Nagari Developer

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700010802
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021originally December 2019
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Ambarnath East

Other MahaRERA-registered projects in the same locality β€” useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.