PropPin
🏗️
Under construction

ATMIYA HEIGHTS

MahaRERA P51700015091High risk

by AKSHAR GROUP

GAT NO 761,762, 78 and Gat no 812, 82, SONIVALI, 421503

Official record
Dec 2025
Possession
83.3%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 83.3%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2025 per the RERA filing.

Area guide

What it's like to buy in SONIVALI

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
AKSHAR GROUP

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700015091
Status
Ongoing
Stage
Certificate Signed
Possession
December 2025
Construction
83.3% complete
Units sold
0 of 0

Similar projects in SONIVALI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.