High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2021, now proposed Oct 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2023) has passed with construction at 81.8%.

Promoter

Builder profile

Builder
BHARAT REALTY VENTURE PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700015290
Status
Ongoing
Stage
Certificate Signed
Possession
October 2023originally December 2021
Construction
81.8% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.