PropPin
Caution
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 81.8%.

Promoter

Builder profile

Builder
ADESHWAR DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700019075
Status
New
Stage
Certificate Signed
Possession
December 2021
Construction
81.8% complete
Units sold
0 of 1

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.