Official record
Mar 2025
Possession
99.4%
Built
10
Complaints
0
Units
High risk
  • 10 RERA complaints. 10 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 99.4%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Mar 2025 per the RERA filing.

Promoter

Builder profile

Builder
HORIZON PROJECTS PVT LTD

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700019085
Status
New
Stage
Certificate Signed
Possession
March 2025
Construction
99.4% complete
Units sold
0 of 0