SILICON TOWER
MahaRERA P51700019695High risk
by SHREE RADHAKRISHNA DEVELOPER
SURVEY NO 50 AND 93 HISSA NO 15 AND 16, KULGAON, 421503
Post your property hereOwn or renting out a unit in SILICON TOWER? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in KULGAON come to you.
Feb 2022
Possession
81.8%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Feb 2022) has passed with construction at 81.8%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Feb 2022 per the RERA filing.
Promoter
Builder profile
SHREE RADHAKRISHNA DEVELOPER
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51700019695
- Status
- New
- Stage
- Certificate Signed
- Possession
- February 2022originally December 2021
- Construction
- 81.8% complete
- Units sold
- 0 of 0
Similar projects in KULGAON
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
VARUN VISTA
KULGAONPoss. December 2028
KRISHNA SUDAMA RESIDENCY
KULGAON90.9% builtPoss. September 2026
RATHADIA CO-OPERATIVE HOUSING SOCIETY LTD
KULGAON90.9% builtPoss. March 2019
SAISHIV COMPLEX
KULGAON90.9% builtPoss. December 2023
TRIDENT TOWER TYPE C
KULGAON78.2% builtPoss. December 2022
MANISHA CO-OP HOUSING SOCIETY
KULGAON73.5% builtPoss. December 2024
SACHINAM CO OP HSG SOCIETY
KULGAON63.6% builtPoss. March 2024
NEW VANRAI PARAG CHS
KULGAON53.2% builtPoss. December 2026
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.