UNNATHI WOODS PHASE VIII
250/1/A, 250/2/A,250/3,251/5A, 244/13, 244/14/2, 244/16, 242/1/1 P, KAVESAR, 400615
- Possession delayed ~3 yrs. Originally promised Jun 2025, now proposed Dec 2027 per the RERA filing.
- 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
Area guide
What it's like to buy in KAVESAR
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P51700020921
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally June 2025
- Construction
- 88.2% complete
- Units sold
- 238 of 296
Similar projects in KAVESAR
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.