PropPin
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Jan 2027 per the RERA filing.
  • Behind schedule. Possession is due Jan 2027 but construction is only at 30%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2027 per the RERA filing.
Ambernath / BadlapurValue

The value frontier beyond Kalyan β€” low-rise affordability, improving rail links.

Growth drivers:
Extended suburban rail, industrial-belt employment, lowest entry prices in MMR.
Who buys here:
First-home buyers stretching every rupee.

PropPin area guide β€” editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
SHREENATH DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700021992
Status
New
Stage
Certificate Signed
Possession
January 2027originally December 2023
Construction
30% complete
Units sold
0 of 0

Similar projects in AMBERNATH

Other MahaRERA-registered projects in the same locality β€” useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.