Under construction
TRUSHNA CHS LTD
MahaRERA P51700023568High risk
ORIGINAL SURVEY NO 337, FINAL PLOT NO 362, PANCHPAKHADI, 400602
Post your property hereOwn or renting out a unit in TRUSHNA CHS LTD? List it in seconds β reaches buyers researching this project.Looking to buy or rent here?Post your requirement β sellers & brokers in PANCHPAKHADI come to you.
Jun 2024
Possession
77.5%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 77.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2024 per the RERA filing.
Thane (Ghodbunder belt)Mid-income
A full city of its own β lakes, malls and township-scale supply along Ghodbunder Road.
- Growth drivers:
- Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
- Who buys here:
- Families upgrading to space and amenities without island-city prices.
PropPin area guide β editorial, not a RERA disclosure.
Promoter
Builder profile
Mahesh Shriram Borkar
View the promoterβs full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700023568
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2024
- Construction
- 77.5% complete
- Units sold
- 0 of 0
Similar projects in PANCHPAKHADI
Other MahaRERA-registered projects in the same locality β useful for a like-for-like comparison.
MONICA BY ISHANVI
PANCHPAKHADIPoss. June 2028
JEEVAN CHS LTD
PANCHPAKHADI90.9% builtPoss. October 2023
PRADEEP CO-OPERATIVE HOUSING SOCIETY LTD.
PANCHPAKHADI90.9% builtPoss. September 2027
MANOHAR MAHAL
PANCHPAKHADI81.8% builtPoss. December 2025
RAHUL CO.OP. HOUSING SOCIETY LTD
PANCHPAKHADI80% builtPoss. February 2025
Kalika Heights Phase II
PANCHPAKHADI79.8% builtPoss. June 2027
SHREE KRUPA CO OP HOUSING SOCIETY
PANCHPAKHADI66.4% builtPoss. September 2026
EMPIRE PRESIDENCY
PANCHPAKHADI50% builtPoss. July 2027