All RERA projects
ποΈ
Under construction
THARWANI MILLENNIUM CITY PHASE III
MahaRERA P51700023784High risk
63/1/1/2AP 63/1/2/2C 63/1/3A 63/1/4 64/1 64/2A 64/3B 64/4P, BADLAPUR, 421503
Post your property hereOwn or renting out a unit in THARWANI MILLENNIUM CITY PHASE III? List it in seconds β reaches buyers researching this project.Looking to buy or rent here?Post your requirement β sellers & brokers in BADLAPUR come to you.
Dec 2026
Possession
0%
Built
2
Complaints
0
Units
High risk
- Behind schedule. Possession is due Dec 2026 but construction is only at 0%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Ambernath / BadlapurValue
The value frontier beyond Kalyan β low-rise affordability, improving rail links.
- Growth drivers:
- Extended suburban rail, industrial-belt employment, lowest entry prices in MMR.
- Who buys here:
- First-home buyers stretching every rupee.
PropPin area guide β editorial, not a RERA disclosure.
Promoter
Builder profile
THARWANI REALTORS
View the promoterβs full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700023784
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 0% complete
- Units sold
- 0 of 0
Similar projects in BADLAPUR
Other MahaRERA-registered projects in the same locality β useful for a like-for-like comparison.
AMBER SOLITAIRE WING A
BADLAPURPoss. January 2030
OMKAR PLAZA D AND E WING
BADLAPURPoss. June 2027
SHREE ASTHAVINAYAK COMPLEX BUILDING NO.1
BADLAPURPoss. June 2028
AMBER SOLITAIRE WING B
BADLAPURPoss. July 2029
SHREEJI SQUARE PHASE I
BADLAPUR103.6% builtPoss. June 2026
PATHAK RESIDENCY
BADLAPUR100% builtPoss. December 2023
SHREE RAJ
BADLAPUR100% builtPoss. April 2019
UNIQUE HEIGHT
BADLAPUR90.9% builtPoss. January 2025
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.