High risk
  • Possession date passed. The proposed possession date (Jul 2020) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2020 per the RERA filing.

Promoter

Builder profile

Builder
Lodha Developers Limited

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700025535
Status
New
Stage
Certificate Signed
Possession
July 2020
Construction
81.8% complete
Units sold
0 of 0