All RERA projects
🏗️
Under construction
SHREE BUILDERS AND DEVELOPERS
MahaRERA P51700026331High risk
by M/S SHREE BUILDERS AND DEVELOPERS
229, DOMBIVALI EAST, 421201
Post your property hereOwn or renting out a unit in SHREE BUILDERS AND DEVELOPERS? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in DOMBIVALI EAST come to you.
Nov 2022
Possession
0.9%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Nov 2022) has passed with construction at 0.9%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Nov 2022 per the RERA filing.
Promoter
Builder profile
M/S SHREE BUILDERS AND DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51700026331
- Status
- New
- Stage
- Certificate Signed
- Possession
- November 2022
- Construction
- 0.9% complete
- Units sold
- 0 of 0
Similar projects in DOMBIVALI EAST
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
MAHAAVIR PRIDE
DOMBIVALI EAST83.9% builtPoss. June 2027
EMERALD
DOMBIVALI EAST81.8% builtPoss. December 2026
ASHTAVINAYAK DARSHAN
DOMBIVALI EAST42.3% builtPoss. August 2028
VISHNU SHAHU CONSTRUCTION
DOMBIVALI EAST0% builtPoss. April 2024
SHREE SWAMI SAMARTH ENTERPRISES
DOMBIVALI EAST0% builtPoss. December 2025
SAMARTH DEVELOPERS
DOMBIVALI EAST0% builtPoss. December 2022
BALAJI RAGHAV
DOMBIVALI EAST0% builtPoss. December 2027
SUNSHINE DEVELOPERS
DOMBIVALI EAST0% builtPoss. December 2023
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.