Under construction

SARVODAYGREENS

MahaRERA P51700026551Caution

by GIRIRAJ REALTORS

107/1 90/4 89/2/1 90/3 110/2 110/1 110/1/6 107/2 110/1/2 110/1/7, SONALE BHADAD, 421302

Official record
Jun 2024
Possession
90.9%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 90.9%.

Promoter

Builder profile

Builder
GIRIRAJ REALTORS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700026551
Status
New
Stage
Certificate Signed
Possession
June 2024
Construction
90.9% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.