Under construction

ASHLAR TATTVA

MahaRERA P51700027399High risk

by AKSHAR ENTERPRISES

S NO.15 H NO.3A, 3B/1 ,3B/2, SNO.16, H NO7/4 S NO.16, H NO.4/1, MANDA, 421605

Official record
Jun 2027
Possession
32.7%
Built
0
Complaints
139
Units
High risk
  • Mortgaged to a lender (₹24 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹24 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Behind schedule. Possession is due Jun 2027 but construction is only at 32.7%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2027 per the RERA filing.

Area guide

What it's like to buy in MANDA

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
AKSHAR ENTERPRISES

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700027399
Status
New
Stage
Certificate Signed
Possession
June 2027
Construction
32.7% complete
Units sold
71 of 139

Similar projects in MANDA

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.