High risk
  • Possession delayed ~2 yrs. Originally promised Jul 2024, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Promoter

Builder profile

Builder
SUNRISE BUILDERS AND DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Anirudddha s Dastane

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51700031031
Status
New
Stage
Certificate Signed
Possession
December 2026originally July 2024
Construction
77.3% complete
Units sold
35 of 68