GEETAI SMRUTI

MahaRERA P51700032519High risk

by NEELPADMA DEVELOPERS

93/A/Part, Plot No 82 And 83, Near DNC School, 421201

Official record
Dec 2026
Possession
43.4%
Built
0
Complaints
28
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 43.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Promoter

Builder profile

Builder
NEELPADMA DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Mr. Shirish G. Nachane

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51700032519
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
43.4% complete
Units sold
10 of 28

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.