Under construction

Riverwood Park Building No -1

MahaRERA P51700032548High risk

by Shree Khidkaleshwar Property Developers Pvt. Ltd.

S. No. 29part, S. No. 30 Hissa No. 1part, Hissa No. 2part, Sagarli , Dombivali East, 421204

Official record
Mar 2027
Possession
41.1%
Built
1
Complaints
170
Units
High risk
  • Mortgaged to a lender (₹50 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹50 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Mar 2027 per the RERA filing.
  • Behind schedule. Possession is due Mar 2027 but construction is only at 41.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Area guide

What it's like to buy in Sagarli , Dombivali East

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Shree Khidkaleshwar Property Developers Pvt. Ltd.

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Vasturachna

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700032548
Status
New
Stage
Certificate Signed
Possession
March 2027originally December 2025
Construction
41.1% complete
Units sold
101 of 170

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.