All RERA projects
🏗️
Under construction
Tulsi Galaxy
MahaRERA P51700033355High risk
S No 69 H No 16, S No 69 H No.17, S no. 69 H No. 17P B, S No. 51, H No.5, NA, 421501
Post your property hereOwn or renting out a unit in Tulsi Galaxy? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in NA come to you.
Mar 2027
Possession
0%
Built
0
Complaints
354
Units
High risk
- Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Mar 2027 per the RERA filing.
- Behind schedule. Possession is due Mar 2027 but construction is only at 0%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
Promoter
Builder profile
Manas Associates
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700033355
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027originally December 2025
- Construction
- 0% complete
- Units sold
- 162 of 354
Similar projects in NA
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Mahakali Greens
NAPoss. March 2027
Mahalaxmi CIty Part-2
NAPoss. March 2025
Bundele Nagari-1
NAPoss. March 2023
SG ESTATE - 2
NAPoss. March 2026
Vrundavan Park- Residential Layout Plan In Survey No-82
NAPoss. March 2024
PRIVARA VIHAR-5
NAPoss. April 2027
PRESTIGE PLATINUM
NAPoss. January 2030
Sai Park-2 Residential Layout Plan
NAPoss. March 2025