PropPin
All RERA projects
🏗️
Under construction

Tulsi Galaxy

MahaRERA P51700033355High risk

by Manas Associates

S No 69 H No 16, S No 69 H No.17, S no. 69 H No. 17P B, S No. 51, H No.5, NA, 421501

Official record
Mar 2027
Possession
0%
Built
0
Complaints
354
Units
High risk
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Mar 2027 per the RERA filing.
  • Behind schedule. Possession is due Mar 2027 but construction is only at 0%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Promoter

Builder profile

Builder
Manas Associates

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700033355
Status
New
Stage
Certificate Signed
Possession
March 2027originally December 2025
Construction
0% complete
Units sold
162 of 354

Similar projects in NA

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.