KEYUR CO-OPERATIVE HOUSING SOCIETY LTD
PLOT NO 308, AMBERNATH, 421501
- Possession delayed ~4 yrs. Originally promised Dec 2025, now proposed Dec 2029 per the RERA filing.
Area guide
What it's like to buy in AMBERNATH
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
A full city of its own β lakes, malls and township-scale supply along Ghodbunder Road.
- Growth drivers:
- Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
- Who buys here:
- Families upgrading to space and amenities without island-city prices.
PropPin area guide β editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoterβs full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700045253
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2029originally December 2025
- Construction
- 9.1% complete
- Units sold
- 8 of 22
Similar projects in AMBERNATH
Other MahaRERA-registered projects in the same locality β useful for a like-for-like comparison.
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.