Under construction

Charms Padamavati Royal Phase 2

MahaRERA P51700045389High risk

by Charms Developers

89/1A, 95/1A, 95/2, 95/10, S No 89 1A, 95 1A 95 2 and 95 10, 421605

Official record
Apr 2027
Possession
33.9%
Built
0
Complaints
746
Units
High risk
  • Behind schedule. Possession is due Apr 2027 but construction is only at 33.9%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Apr 2027 per the RERA filing.

Area guide

What it's like to buy in S No 89 1A, 95 1A 95 2 and 95 10

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Charms Developers

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Momin Sajid

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700045389
Status
New
Stage
Certificate Signed
Possession
April 2027
Construction
33.9% complete
Units sold
96 of 746

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.